CUP: D77B04000370007
INTERVENTI FINALIZZATI ALLA MITIGAZIONE DEL RISCHIO DA CROLLO DALLE PARETI DI MONTE PELLEGRINO SOVRASTANTI GLI ABITATI DI ADDAURA E MONDELLO NEL COMUNE DI PALERMO CODICE RENDIS 19IRB91/G1
SUMMARY OF THE PROJECT
INTERVENTI FINALIZZATI ALLA MITIGAZIONE DEL RISCHIO DA CROLLO DALLE PARETI DI MONTE PELLEGRINO SOVRASTANTI GLI ABITATI DI ADDAURA E MONDELLO NEL COMUNE DI PALERMO CODICE RENDIS 19IRB91/G1
This project is no longer active and is therefore excluded from totals and search results
Funding monitored
€ 1,088,675.70
of which cohesion funds
€ 1,088,675.70
Given name | Amount |
---|---|
Development and Cohesion Fund | 1088675.70 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: not available
Effective start: not available
Expected end: not available
Effective end: not available
Entities
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PIANO FSC DISSESTO IDROGEOLOGICO - FONDO PROGETTAZIONE
- DCF strategic sector
- Ambiente
- DCF area axis
- Cambiamento climatico, prevenzione e gestione dei rischi ambientali
Other projects in territory
Same theme
Same type of investment
SISTEMA TRAM CITTA' DI PALERMO | € 298,886,604 |
RADDOPPIO FERROVIARIO PALERMO - CARINI - TRATTA B - NOTABARTOLO - EMS/LA MALFA | € 290,894,000 |
SISTEMA TRAM PALERMO - FASE II | € 254,067,537 |
REALIZZAZIONE DELLA CHIUSURA DELL'ANELLO FERROVIARIO DI PALERMO | € 152,095,271 |
COMPLETAMENTO COLLETTORE FOGNARIO DELLA ZONA SUD-EST DI PALERMO. (33414) | € 47,313,795 |