CUP: G24B13000220002
NODO IDRAULICO DI MONDINE: COMPLETAMENTO IMPIANTO IDROVORO
SUMMARY OF THE PROJECT
NODO IDRAULICO DI MONDINE: COMPLETAMENTO IMPIANTO IDROVORO
Implementation indicator
Superficie oggetto di intervento
- Target
- 5,250 mq
- Achieved
- 5,250 mq
Funding monitored
€ 5,876,533.74
of which cohesion funds
€ 5,876,533.74
Given name | Amount |
---|---|
Development and Cohesion Fund | 5876533.74 |
- Economies:
- € 123,466.26
Payments monitored
€ 5,876,533.74
of which cohesion funds
€ 5,876,533.74
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 136225.43 | 136225.43 | 2 |
2015 | 575000.00 | 711225.43 | 12 |
2016 | 2746425.65 | 3457651.08 | 58 |
2017 | 1800526.01 | 5258177.09 | 89 |
2018 | 73610.41 | 5331787.50 | 90 |
2019 | 544746.24 | 5876533.74 | 100 |
State of progress
Completed
Expected start: 25/08/2014
Effective start: 25/08/2014
Expected end: 30/11/2017
Effective end: 30/11/2017
Entities
- Planning body
- REGIONE EMILIA-ROMAGNA
- Implementing body
- CONSORZIO DI BONIFICA DELL'EMILIA CENTRALE
- Beneficiary
- CONSORZIO DI BONIFICA DELL'EMILIA CENTRALE
- Executor
- PARENTI COSTRUZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC EMILIA-ROMAGNA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
IDROVORA DI MONDINE - NUOVO IMPIANTO IRRIGUO | € 2,506,020 |
CHIAVICA EMISSARIA DI MONDINE: NUOVA CHIAVICA | € 2,454,651 |
MAGAZZINO DI MONDINE: RIPRISTINO E MIGLIORAMENTO SISMICO | € 189,758 |