CUP: B34H15000030001
ADEGUAMENTO FUNZIONALE/ENERGETICO DELLA PISCINA COMUNALE DI MONTEREALE
SUMMARY OF THE PROJECT
ADEGUAMENTO FUNZIONALE/ENERGETICO DELLA PISCINA COMUNALE DI MONTEREALE
Implementation indicator
Riduzione nei consumi energetici
- Target
- 100 tep
- Achieved
- 100 tep
Funding monitored
€ 610,177.95
of which cohesion funds
€ 610,177.95
Given name | Amount |
---|---|
Development and Cohesion Fund | 610177.95 |
- Economies:
- € 4,822.05
Payments monitored
€ 610,177.95
of which cohesion funds
€ 610,177.95
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 13696.61 | 13696.61 | 2 |
2017 | 190712.55 | 204409.16 | 33 |
2018 | 203854.94 | 408264.10 | 66 |
2019 | 14421.26 | 422685.36 | 69 |
2020 | 179871.82 | 602557.18 | 98 |
2021 | 7620.77 | 610177.95 | 100 |
State of progress
Completed
Expected start: 22/05/2017
Effective start: 05/06/2017
Expected end: 31/12/2020
Effective end: 28/01/2020
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- REGIONE BASILICATA
- Beneficiary
- REGIONE BASILICATA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici