CUP: E61B15000060002
S.P. 23 DI CELLINO REALIZZAZIONE DEL NUOVO PONTE DI CASTELNUOVO' SUL FIUME VOMANO
SUMMARY OF THE PROJECT
S.P. 23 DI CELLINO REALIZZAZIONE DEL NUOVO PONTE DI CASTELNUOVO' SUL FIUME VOMANO
Implementation indicator
Estensione in lunghezza
- Target
- 1.53 km
- Achieved
- 1.53 km
Funding monitored
€ 5,786,247.54
of which cohesion funds
€ 2,989,561.24
Given name | Amount |
---|---|
Development and Cohesion Fund | 2989561.24 |
Region | 2796686.30 |
- Economies:
- € 213,752.46
Payments monitored
€ 4,606,624.92
of which cohesion funds
€ 2,354,362.43
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 2806.00 | 2806.00 | 0 |
2016 | 0 | 2806.00 | 0 |
2017 | 0 | 2806.00 | 0 |
2018 | 182140.23 | 184946.23 | 3 |
2019 | 87255.67 | 272201.90 | 4 |
2020 | 229055.02 | 501256.92 | 8 |
2021 | 1661936.49 | 2163193.41 | 37 |
2022 | 607766.22 | 2770959.63 | 47 |
2023 | 1835665.29 | 4606624.92 | 79 |
State of progress
Open
Expected start: 01/11/2022
Effective start: not available
Expected end: 30/11/2022
Effective end: not available
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI TERAMO
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI TERAMO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto Stradale