CUP: B34H17000950001
PATTO CITTA' DI GENOVA RIO VERNAZZA E TORRENTE STURLA VIA PONTETTI ADEGUAMENTO E MESSA IN SICUREZZA - 2' STRALCIO SCOLMATORE E VIA PONTETTI
SUMMARY OF THE PROJECT
PATTO CITTA' DI GENOVA RIO VERNAZZA E TORRENTE STURLA VIA PONTETTI ADEGUAMENTO E MESSA IN SICUREZZA - 2' STRALCIO SCOLMATORE E VIA PONTETTI
Implementation indicator
Ampliamento di portata
- Target
- 140 mc/s
- Achieved
- 0 mc/s
Funding monitored
€ 11,000,000.00
of which cohesion funds
€ 11,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 11000000.00 |
Payments monitored
€ 8,246,001.82
of which cohesion funds
€ 8,246,001.82
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 122622.12 | 122622.12 | 1 |
2020 | 2381750.31 | 2504372.43 | 22 |
2021 | 182098.06 | 2686470.49 | 24 |
2022 | 1688642.27 | 4375112.76 | 39 |
2023 | 3870889.06 | 8246001.82 | 74 |
State of progress
Open
Expected start: 01/01/2020
Effective start: 24/03/2021
Expected end: 16/06/2022
Effective end: not available
Entities
- Planning body
- COMUNE DI GENOVA
- Implementing body
- COMUNE DI GENOVA
- Beneficiary
- COMUNE DI GENOVA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CITTA' METROPOLITANA DI GENOVA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico