CUP: J83G15001250005
CONSOLIDAMENTO DISSESTO IDROGEOLOGICO AREA A PERICOLOSITÃ FRANA MOLTO ELEVATA VIA DI VITTORIO
SUMMARY OF THE PROJECT
CONSOLIDAMENTO DEL PENDIO CON PARATIE DI GROSSO DIAMETRO ANCORATE A PALI E REGIMENTAZIONE DELLE ACQUE.
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 500 num
- Achieved
- 0 num
Funding monitored
€ 3,511,380.00
of which cohesion funds
€ 3,511,380.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3511380.00 |
Payments monitored
€ 358,228.89
of which cohesion funds
€ 358,228.89
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 9873.30 | 9873.30 | 0 |
2020 | 12416.77 | 22290.07 | 0 |
2021 | 294938.82 | 317228.89 | 9 |
2022 | 15000.00 | 332228.89 | 9 |
2023 | 26000.00 | 358228.89 | 10 |
State of progress
Open
Expected start: 01/02/2025
Effective start: not available
Expected end: 30/10/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE-DIREZIONE GENERALE PER LA SALVAGUARDIA DEL TERRITORIO E DELLE ACQUE
- Implementing body
- COMMISSARIO STRAORDINARIO PER L'ATTUAZIONE DEGLI INTERVENTI PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO NELLA REGIONE PUGLIA
- Beneficiary
- COMMISSARIO STRAORDINARIO PER L'ATTUAZIONE DEGLI INTERVENTI PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO NELLA REGIONE PUGLIA
- Executor
-
RTI COPPOLELLA DONATO
PLANETEK ITALIA SRL
ING. LOBEFARO ANGELO
ING. CARBONE FILOMENA
APOGEO SRL
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico