CUP: B31G11000000003
ADEGUAMENTO DELLA VASCA DI COLMATA REALIZZATA NELL'AMBITO DEI LAVORI DI II FASE DELLE OPERE A MARE IN ATTUAZIONE DEL VIGENTE P.R.P. NEL PORTO DI ANCONA
This project is no longer active and is therefore excluded from totals and search results
Funding monitored
€ 7,167,893.56
of which cohesion funds
€ 1,826,028.92
Given name | Amount |
---|---|
Development and Cohesion Fund | 1826028.92 |
Status: other measures | 2149276.21 |
Municipality | 559525.81 |
Another public source | 2633062.62 |
- Economies:
- € 2,832,106.44
Payments monitored
€ 7,167,893.56
of which cohesion funds
€ 1,826,028.92
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 305309.16 | 305309.16 | 4 |
2012 | 0 | 305309.16 | 4 |
2013 | 0 | 305309.16 | 4 |
2014 | 6608131.00 | 6913440.16 | 96 |
2015 | 254453.40 | 7167893.56 | 100 |
State of progress
Completed
Expected start: 22/05/2013
Effective start: 22/05/2013
Expected end: 31/12/2014
Effective end: 27/11/2014
Entities
- Priority QSN
- Reti e collegamenti per la mobilità
- General objective QSN
- Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
- Specific objective QSN
- Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PAR FSC MARCHE
- Line
- Sviluppo e miglioramento della dotazione delle infrastrutture portuali e aeroportuali.
- Action
- Attuazione dell'Accordo di Programma Quadro per i dragaggi e lo sviluppo sostenibile delle aree portuali