CUP: D89H10000840006
NUOVO POLO SCOLASTICO VIA GIOVANNI XXIII REALIZZAZIONE IMPIANTI TECNOLOGICI SCUOLA ELEMENTARE
Funding monitored
€ 250,386.71
of which cohesion funds
€ 250,386.71
Given name | Amount |
---|---|
European Union | 99253.29 |
Status: other measures | 150632.64 |
Region | 500.78 |
Payments monitored
€ 250,386.71
of which cohesion funds
€ 250,386.71
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 147916.49 | 147916.49 | 59 |
2015 | 102470.22 | 250386.71 | 100 |
State of progress
Completed
Expected start: 11/04/2013
Effective start: 11/04/2013
Expected end: 03/09/2013
Effective end: 03/09/2013
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE LOMBARDIA
- Implementing body
- COMUNE DI GIUSSAGO
- Beneficiary
- COMUNE DI GIUSSAGO
- Executor
- COMUNE DI GIUSSAGO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF LOMBARDY
- Axis
- Energia
- Operational objective
- Incremento della produzione energetica da fonti rinnovabili e sviluppo della cogenerazione.