CUP: E11B08000170002
OPERE DI REALIZZAZIONE ILLUMINAZIONE PIBBLICA STRADALE
Funding monitored
€ 443,429.94
of which cohesion funds
€ 443,429.94
Given name | Amount |
---|---|
European Union | 175775.63 |
Status: other measures | 266767.45 |
Region | 886.86 |
Payments monitored
€ 443,429.94
of which cohesion funds
€ 443,429.94
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 193191.59 | 193191.59 | 43 |
2013 | 250435.67 | 443627.26 | 100 |
2014 | 0 | 443627.26 | 100 |
2015 | 0 | 443627.26 | 100 |
2016 | -197.32 | 443429.94 | 100 |
State of progress
Completed
Expected start: 21/06/2011
Effective start: 21/06/2011
Expected end: 31/12/2011
Effective end: 31/12/2011
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE LOMBARDIA
- Implementing body
- COMUNE DI VEDUGGIO CON COLZANO
- Executor
- COMUNE DI VEDUGGIO CON COLZANO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF LOMBARDY
- Axis
- Energia
- Operational objective
- Riduzione dei consumi energetici.
Other projects in territory
Same type of investment
BANDA ULTRALARGA NELLE AREE BIANCHE DEL TERRITORIO DELLA REGIONE LOMBARDIA CON FONDI FSC | € 196,866,863 |