CUP: E52H11000020001
Lavori urgenti di completamento del consolidamento al piede della piazza e della viabilità denominata area mercatale
SUMMARY OF THE PROJECT
opere di consolidamento del versante
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 370,000.00
of which cohesion funds
€ 350,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 350000.00 |
Municipality | 20000.00 |
Payments monitored
€ 324,041.50
of which cohesion funds
€ 306,533.59
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 18670.73 | 18670.73 | 5 |
2021 | 35038.25 | 53708.98 | 14 |
2022 | 236474.90 | 290183.88 | 78 |
2023 | 33857.62 | 324041.50 | 87 |
State of progress
Open
Expected start: 01/10/2021
Effective start: 06/04/2022
Expected end: 03/09/2022
Effective end: 03/10/2023
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI BOSSOLASCO
- Beneficiary
- REGIONE PIEMONTE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 350,000.00
- Payments on cohesion funds
- € 306,533.59
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico