CUP: I19E19000980005
LAVORI DI MESSA IN SICUREZZA E RIQUALIFICAZIONE ENERGETICA TRAMITE SOSTITUZIONE DI SERRAMENTI ESTERNI PRESSO SCUOLA PRIMARIA DI COLORNO ANNO 2019
SUMMARY OF THE PROJECT
LAVORI DI MESSA IN SICUREZZA E RIQUALIFICAZIONE ENERGETICA TRAMITE SOSTITUZIONE DI SERRAMENTI ESTERNI PRESSO SCUOLA PRIMARIA DI COLORNO
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 130,000 num
- Achieved
- 113,425.13 num
Download project
Funding monitored
€ 113,425.13
of which cohesion funds
€ 70,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 70000.00 |
Municipality | 43425.13 |
- Economies:
- € 16,574.87
Payments monitored
€ 70,000.00
of which cohesion funds
€ 70,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 70000.00 | 70000.00 | 61 |
State of progress
Open
Expected start: 31/10/2019
Effective start: 31/10/2019
Expected end: 30/09/2020
Effective end: 08/10/2020
Entities
- Planning body
- COMUNE DI COLORNO
- Beneficiary
- COMUNE DI COLORNO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 70,000.00
- Payments on cohesion funds
- € 70,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile