CUP: G73B14000020002
SISTEMAZIONI IDRAULICO FORESTALI A BASSO IMPATTO PER LA DIFESA DEL SUOLO INTERVENTI SUI CORSI D'ACQUA SUI VERSANTI E SULLA VIABILITA' IN LOCALITA' "MALPASSO GIUMENTARELLO FORTOLESE S.FRANCESCO BUBBONETTO" IN TERRITORIO DI ENNA E VILLAROSA
Funding monitored
€ 903,612.22
of which cohesion funds
€ 903,612.22
Given name | Amount |
---|---|
Revolving Fund (Cohesion Action Plan) | 903612.22 |
Payments monitored
€ 533,384.21
of which cohesion funds
€ 533,384.21
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 111759.61 | 111759.61 | 12 |
2016 | 237765.70 | 349525.31 | 38 |
2017 | 183858.90 | 533384.21 | 59 |
State of progress
Open
Expected start: 11/11/2014
Effective start: 11/11/2014
Expected end: 31/12/2015
Effective end: 31/12/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Environment
- Prevenzione dei rischi (inclusa elaborazione e attuazione di piani e provvedimenti))
Territory
Entities
- Planning body
- REGIONE SICILIANA
- Implementing body
- REGIONE SICILIANA
- Beneficiary
- REGIONE SICILIANA
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- 2007-2013 Cohesion Action Plan
- 2007-2013 Cohesion Action Plan
- Programme
- PROGRAMMA PAC SICILIA
- Line
- Nuove Azioni
- Action
- Interventi di mitigazione del rischio idrogeologico