CUP: B66J13002710005
INTERVENTI DI RISTRUTTURAZIONE E MESSA IN SICUREZZA DELLE SCUOLE MEDIE CITTADINE E COMPLETAMENTO DELLE OPERE GIA ESEGUITE SULLA BASE DELLA DEL.CIPE 03/2009SEDE DI VIA MATILDE CERETTI
This project is eliminated from views and totals because it is a duplicate of the project:
Funding monitored
€ 596,783.30
of which cohesion funds
€ 497,319.42
Given name | Amount |
---|---|
Development and Cohesion Fund | 497319.42 |
Municipality | 99463.88 |
- Economies:
- € 3,216.70
Payments monitored
€ 595,251.86
of which cohesion funds
€ 496,043.22
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 578506.68 | 578506.68 | 96 |
2016 | 16745.18 | 595251.86 | 99 |
State of progress
Completed
Expected start: 12/06/2015
Effective start: 12/06/2015
Expected end: 08/11/2015
Effective end: 25/02/2016
Type
- Infrastructure
- AMPLIAMENTO O POTENZIAMENTO
Theme
- Education and training
- Infrastrutture per l'istruzione
Territory
Entities
- Planning body
- MIUR ISTRUZIONE
- Implementing body
- COMUNE DI DOMODOSSOLA
- Beneficiary
- COMUNE DI DOMODOSSOLA
- Executor
- COMUNE DI DOMODOSSOLA
- Priority QSN
- Miglioramento e valorizzazione delle risorse umane
- General objective QSN
- Innalzare i livelli di apprendimento e di competenze chiave, l'effettiva equità di accesso ai percorsi migliori, aumentare la copertura dei percorsi di istruzione e formazione iniziale
- Specific objective QSN
- Accrescere il tasso di partecipazione all'istruzione e formazione iniziale
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PROGRAMMA ATTUATIVO MIUR MESSA IN SICUREZZA EDIFICI SCOLASTICI
- Line
- Riqualificazione e messa in sicurezza delle istituzioni scolastiche statali
- Action
- ulteriori interventi finanziabili ai sensi art. 18 DL 69/2013