CUP: G23J06000080002
Collegamento isola Palmaria - Porto Venere
SUMMARY OF THE PROJECT
Collegamento isola Palmaria - Porto Venere
Implementation indicator
Estensione della rete
- Target
- 0.55 km
- Achieved
- 0.55 km
Download project
Funding monitored
€ 98,643.27
of which cohesion funds
€ 98,643.27
Given name | Amount |
---|---|
Development and Cohesion Fund | 98643.27 |
- Other resources - Private:
- € 215,243
Payments monitored
€ 98,643.27
of which cohesion funds
€ 98,643.27
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 21068.30 | 21068.30 | 21 |
2009 | 0 | 21068.30 | 21 |
2010 | 21919.90 | 42988.20 | 43 |
2011 | 43079.92 | 86068.12 | 87 |
2012 | 5900.14 | 91968.26 | 93 |
2013 | 0 | 91968.26 | 93 |
2014 | 0 | 91968.26 | 93 |
2015 | 0 | 91968.26 | 93 |
2016 | 6675.01 | 98643.27 | 100 |
State of progress
Completed
Expected start: 22/02/2010
Effective start: 22/02/2010
Expected end: 21/11/2011
Effective end: 21/11/2011
Entities
- Planning body
- ISTITUTO NAZIONALE DELLA PREVIDENZA SOCIALE - INPS
- Implementing body
- PROVVEDITORATO OO.PP. PER LA LOMBARDIA
- Beneficiary
- ISTITUTO NAZIONALE DELLA PREVIDENZA SOCIALE - INPS
Programming area
- Programme
- PSC REGIONE LIGURIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 98,643.27
- Payments on cohesion funds
- € 98,643.27
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche