Updated on 30/04/2025
Funding monitored € 393,190.66 of which cohesion funds € 359,769.45
Given name Amount
Development and Cohesion Fund359769.45
Status: other measures33421.21
Economies:
€ 26,809.34
Payments monitored € 393,190.66 of which cohesion funds € 369,692.20
Year Amount Cumulative amount Percentage on public financing
201330814.9730814.977
2014156088.84186903.8147
201526165.65213069.4654
20160213069.4654
20170213069.4654
20180213069.4654
20190213069.4654
2020180121.20393190.66100

State of progress

Completed
Expected start: 08/07/2014
Effective start: 08/07/2014
Expected end: 02/09/2014
Effective end: 02/09/2014

Type

Theme

  • Environment
  • Altre misure per tutelare l'ambiente e prevenire i rischi

Territory

Entities

Planning body
MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
Implementing body
COMMISSARIO STRAORDINARIO DELEGATO ALL¿ATTUAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO DI CUI ALL¿ACCORDO DI PROGRAMMA TRA IL MINISTERO DELL¿AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE E LA REGIONE PIEMONTE (D.P.C.M. 19 APRILE 2011)
Beneficiary
COMUNE DI PRUNETTO
Executor
COMUNE DI PRUNETTO
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

Programme
PROGRAMMA NAZIONALE DI ATTUAZIONE (PNA) FSC RISANAMENTO AMBIENTALE
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 359,769.45
Payments on cohesion funds
€ 369,692.20
Line
Interventi di risanamento ambientale Regione Piemonte
Action
AP per la mitigazione del rischio idrogeologico Regione Piemonte