Updated on 29/02/2024
Funding monitored € 117,200,000.00 of which cohesion funds € 56,400,000.00
Given name Amount
Development and Cohesion Fund56400000.00
Another public source60800000.00
Payments monitored € 12,444,389.32 of which cohesion funds € 12,187,989.31
Year Amount Cumulative amount Percentage on public financing
2018386074.98386074.980
20191712993.282099068.261
20203276656.195375724.454
20212222980.627598705.076
20223360326.6710959031.749
20231485357.5812444389.3210

State of progress

Open
Expected start: 07/05/2018
Effective start: 07/05/2018
Expected end: 31/12/2025
Effective end: not available

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Policy Area
Trasporti e Mobilita'
Sector of intervention
Trasporto ferroviario