Updated on 31/08/2022
Funding monitored € 13,475,350.74 of which cohesion funds € 13,475,350.74
Given name Amount
European Union9163238.50
Revolving Fund (National co-financing)1563140.69
Region2748971.55
Payments monitored € 13,475,350.74 of which cohesion funds € 13,475,350.74
Year Amount Cumulative amount Percentage on public financing
20137658800.007658800.0056
20144886400.0012545200.0093
2015930150.7413475350.74100

State of progress

Completed
Expected start: 12/12/2012
Effective start: 12/12/2012
Expected end: 05/05/2014
Effective end: 05/05/2014

Type

Theme

Territory

Entities

Planning body
REGIONE PUGLIA
Implementing body
FERROVIE DEL SUD EST E SERVIZI AUTOMOBILISTICI SOCIETA A RESPONSABILITA LIMITATA O IN ABBREVAZIONE FSE SRL
Beneficiary
FERROVIE DEL SUD EST E SERVIZI AUTOMOBILISTICI SOCIETA A RESPONSABILITA LIMITATA O IN ABBREVAZIONE FSE SRL
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Promuovere la mobilità urbana sostenibile e la logistica urbana

At the School of OpenCohesion

OpenCoesione goes to School followed this project in edition 2014-15 with the team “CAPOLINEASALENTO” of “IISS DON TONINO BELLO” of Tricase, LECCE.

Programming area

European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Programme
ROP CONV ERDF PUGLIA
Axis
RETI E COLLEGAMENTI PER LA MOBILITA'
Operational objective
4a) Realizzare in ambito urbano e regionale gli interventi infrastrutturali necessari al completamento delle connessioni tra reti ferro-stradali principali e nodi logistici e di trasporto, minimizzando gli impatti ambientali e sul territorio.